Project Details 

  • Client:  University of Leeds
  • Status:  Complete
  • Value:   £371,821.00
  • Duration:  14 weeks

The nature of this project was the internal alterations to form new laboratory accommodation in three rooms located in the existing Physics Deck Building, on level 8.  This is a central location on the main Campus and as such is an extremely busy area. 

The works included:

  • Asbestos abatement works
  • Installation of hygienic wall cladding
  • Fire protection works
  • New internal walls, partitions and doors
  • New suspended ceilings
  • New internal finishes
  • Redecoration
  • Mechanical, electrical and data installations
  • New laboratory furniture